The LRWA has published Version 2.2 of its Hot Melt Code of Practice, effective from 14 August 2026 which has been updated to align with the newly revised BS 6229:2025.   The Code is the industry’s definitive reference for the selection, design, specification, installation and maintenance of hot‑applied polymer‑modified bitumen (hot melt) waterproofing systems, covering everything from zero‑falls and inverted warm roofs through to biodiverse and blue roof build‑ups.   The most significant thread running through this edition is a renewed emphasis on drainage — specifically, achieving correct falls at deck level to eliminate standing water, which remains one of the biggest factors in long‑term roof performance.  

The main recommendations of the code are:

  • A minimum 1:80 finished fall should be achieved in both the general area and any internal gutters.
  • For flat roofs with an area less than or equal to 50 m2, the designed fall should be greater than or equal to 1:60.
  • Inverted roofs or roofs with multi-functional finishes, no back falls should be present where ponding could occur
  • For blue roofs designed with an absolute zero fall, the finished surface should not be constructed with back falls where there is a risk of ponding.
  • In the absence of a structural analysis, prefabricated or site-formed falls should be designed to 1:40
  • Rainfall intensity should be assessed in accordance with BS EN 12056‑3
For any project involving hot melt waterproofing, we’d encourage design‑stage teams to interrogate deck falls and drainage strategy against BS 6229:2025 and the revised Code from the outset. If you’d like any advice on rainwater design, build‑up or falls arrangement against the updated guidance, please get in touch.
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 